Renovation of Zwanenbrug in Halfweg
Temporary Bridge Solution During Renovation of Zwanenbrug in Halfweg
For the renovation of the existing movable section of the Zwanenbrug in Halfweg, it was essential that local traffic—including bus routes and emergency services such as the fire department—could continue to use the bridge connection over the Ringvaart canal of Haarlemmermeer.
Commissioned by Spie Nederland, we constructed a temporary bridge structure on and over the existing abutments. To ensure a smooth connection to the elevated temporary bridge deck, our client installed ramps made of cold asphalt. This solution allowed the bridge to be easily dismantled after the rental period, without causing damage to the original road surface.
Prosjektdetaljer
Løsning
                Bjelkebro
            Type
                JSK-JBB
            Total length
                13,5 m
            width
                4,5 m
            Egen vekt
                In total 36 ton in three elements
            Leie periode
                10 weeks
            Design belastning
                Conform EN1090 excl 3
            